Project Planning Assignment Sample

Introduction

Project planning is part of project management in which effective plan is developed to execute project. In this there is Gantt chart is developed for schedule monitoring. The planning can be done with help of project management software as well (Ika and Saint‐Macary, 2021). It delivers activities into desired outcomes.

Here, report will discuss about conference project undertaken by DDM. It is done to conduct virtual conference with purpose to add more subscriptions.

Project objectives

  • To conduct conference in Birmingham, UK digitally.
  • To create a distinct image of magazine in front of rivals.
  • To debate on issues such as AI, cyber security,

Get Assignment Help from Industry Expert Writers (1)

Expected benefits

  • To gain competitive advantage in market by creating unique image
  • Moreover, to get more payments to be done by people for DDM magazine.

Estimated cost

It is essential to estimate budget required to complete project. So, according to that resources are distributed. It also enables in giving insight of total cost needed in it. Thus, for DDM conference there is approx. budget given of £350,000. The distribution done is below:

Activities Cost
Theatre rent £121,000
Room booking £67,000
Health and safety expenses £12,000
Food and drinks £32,000
Labor wages £21,000
Miscellaneous expenses £10,000
IT staff and infrastructure £8,000

Timescale

It represents the time in which project has to be completed. The schedule is prepared on basis of timeline. Hence, it is necessary that tasks are finished on time and there is no delay in it otherwise project cost rises. This may result in decrease in DDM director satisfaction. So, this entire project time is 7 months that is it begins on April 2022 and finish in October 2022 (Krähmer and Strausz, 2017).

Assumptions

Get Assignment Help from Industry Expert Writers (1)

It is considered as a project factor which can be true, fact or real without any proof. They have to considered as becomes easy to analyse factors. In same way in current DDM conference project assumptions are :

  • Conference is organized successfully by project manager and staff.
  • The quality of catering services in poor and food taste is poor.
  • There is conflict between project manager and team.
  • Also, there is conflict between director and project manager
  • The guests do not get their desire accommodation (Thomas and Kihneman-Wooten, 2018).
  • There can be electricity problem during conference.

Constraints

In project there is a certain risk or limitation which occurs during particular time period. They impact on entire quality and success of project. The constraints are:

  • There is need of additional budget needed.
  • The theatre is overcrowded and it led to disruptions in conference.
  • The speaker may not work properly during conference.

Communication plan

During project it is important to communicate and share data and info clearly (Bryson and Delbecq, 2020). This is because it enables in taking effective decisions. Besides, the plan makes easy and gives clarity that which info is to be shared with whom and how. So, the plan for this project is defined as:

Description Objective of communication Frequency Medium Target audience Owner
Type of communication What is trying to achieve How often it occurs Method Who will receive communication Who is responsible
Project break down It will contain info of project tasks to be carried out Weekly In face to face meeting Project team, DDM director and stakeholders Project manager
Roles and responsibility To assign roles to staff In every 10 days By sending e mail Project team Project manager
Project progress To show how much of project is being completed. Weekly By sending e mail Project team, DDM director and stakeholders Project manager
Ticket sells To find out how many tickets are sold In every 15 days By sending e mail Stakeholders Project team

WBS

It provides break down of project into varied tasks that makes easy for project manager to proceed with it.

Activity list

In this it shows what are different project activities to be carried out along with its predecessors, start, end time.

Task Name Duration Start Finish Predecessors
Planning 77 days Mon 11-04-22 Fri 24-06-22
   Preparation of budget 28 days Mon 11-04-22 Fri 06-05-22
   Choosing of venue 14 days Mon 09-05-22 Fri 20-05-22 2
   Booking 14 days Mon 23-05-22 Fri 03-06-22 3
   Catering facilities 21 days Mon 06-06-22 Fri 24-06-22 4
Speakers 14 days Mon 11-07-22 Fri 22-07-22 5
   Installing speakers 14 days Mon 11-07-22 Fri 22-07-22 7
Event promotion 63 days Mon 25-07-22 Fri 09-09-22 7
   Ticket printing 21 days Mon 25-07-22 Fri 12-08-22 9
   Selling 28 days Mon 15-08-22 Fri 09-09-22 11
Start registration 14 days Mon 12-09-22 Fri 23-09-22 12

Network diagram

The graphical view composed of project integrated tasks mentioned in box and arrow defining relation within them.

Activity Task Name Duration Predecessors
A  Budget 28 days
B    Choosing of venue 14 days A
C    Booking 14 days B
D    Catering facilities 21 days C
E    Installing speakers 14 days D
F Event promotion 63 days E
G Ticket printing 21 days F
H    Selling 28 days G
I Start registration 14 days H

Risk register

There is need to determine risk so that it is mitigated. The main thing is to eliminate risk by taking relevant measures. The risk register is tool used for that. In this all risks are identified along with its impact, probability, action, responsibility (Rettig and Simons, 2019). It is used by manager to manage risks in effective way. Hence, in DDM conference project the risk register is as:

 

Date

 

Risk description

 

Probability

 

Impact

 

Risk rating

Managed response
Action Responsibility Review date Status
1 Project delay 3 7 25 In this schedule is to be developed and then monitoring is done. Project manager 10-5-2022 Done
2 Rise in budget 4 8 20 An additional budget must be prepared Finance team 1-6-2022 Already done
3 Failure of event 5 9 30 There is proper promotion and marketing done. Also, it is ensured that all tickets are sold. Project manager, DDM director. 21-7-2022 In progress
4 Mismanagement of facilities 2 5 10 There is proper monitoring done to all facilities and report prepared. Project manager 23-7-2022 Done
5 Insufficient HR 5 7 10 There should be immediate hiring of labor done. HR team 10-9-2022 Not done

Conclusion

It can be concluded that DDM conference is held to increase subscriptions of magazine. It is 7-month event with £350,000 budget. The risks that can occur are failure of event, delay, moreover, there are certain constraints and assumptions as well.

References

Bryson, J.M. and Delbecq, A.L., (2020). A contingent approach to strategy and tactics in project planning. Journal of the American Planning Association, 45(2), pp.167-179.

Ika, L.A. and Saint‐Macary, J., (2021). The project planning myth in international development. International Journal of Managing Projects in Business.

Krähmer, D. and Strausz, R., (2017). Optimal procurement contracts with pre-project planning. The Review of Economic Studies, 78(3), pp.1015-1041.

Rettig, M. and Simons, G., (2019). A project planning and development process for small teams. Communications of the ACM, 36(10), pp.45-55.

Thomas, M. and Kihneman-Wooten, J., (2018). Developing an effective project: Planning and team building combined. Project Management Journal39(4), pp.105-113.

………………………………………………………………………………………………………………………..

Know more about UniqueSubmission’s other writing services:

Assignment Writing Help

Essay Writing Help

Dissertation Writing Help

Case Studies Writing Help

MYOB Perdisco Assignment Help

Presentation Assignment Help

Proofreading & Editing Help

Leave a Comment