BSS060-6 Project Management Assignment Sample
Module code and Title: BSS060-6 Project Management Assignment Sample
Project Overview
Project objectives
- To attract more airlines from the high-profile and high-paying domains
- To attract more “domestic” and “international passengers” towards “ANR Robinson International Airport” in “Trinidad and Tobago” (Goyalet al. 2021)
- To promote and sell the credentials including greenness and sustainability, location and convenience and others
- To promote the attractiveness of “Trinidad and Tobago” as a tourist attraction in the marketing campaigns (Huo and Guo, 2021)
SN – The objective of the project is to increase the sales and customer intervention of “ANR Robinson International Airport” with the help of “Plane Good Agency” by including “Leadership in Energy” and “Environmental Design” or “LEED”. This is going to be endured dragging traffics in the domestic and international airline operations on the island.
Expected benefits
- Increase influx of tourists, revamping sales, high-paying flights, economic sustainability, employment generation and increase the popularity (Pocinhoet al. 2021)
Estimated costs
- The total estimated cost for the project execution is supposed to be £300,000 (Kopasz and Krause, 2021)
Estimated timescale
- The estimated time required for the marketing project of “Plane Good Agency” is going to be around 8 months (Karayevet al. 2021)
Assumptions and constraints
- The marketing project may face challenges due to high competition from the simar companies, resources may not be optimised
SN – The project also includes the expansion of the “tarmac” and the development of new car parking facilities to improve offerings. The actions of the company may benefit the environmental aspects that can increase the business production and benefit “ANR Robinson International Airport”.
Key planning considerations
- Communication plan development to include local people, investors, and global investors from “New York”, “Orlando”, “Houston”, “Miami”, “Newark”, and “Fort Lauderdale” in the US (Layton and Domegan, 2021)
- Development of three levels of WBS to critically identify the stages
- Development of a network diagram to check the stages of the marketing plan including facility development, budget planning, and influencing customers through the effort of “Plane Good Agency” for “ANR Robinson Airport” (Fischer, 2022)
- Preparing activity list and risk register
The activities are organised according to their complexities and importance for the marketing plan of “ANR Robinson Airport”. In order to evaluate the project through its critical stages, the three-stage WBS is the best preference for the marketing plan development. Strategic considerations are included to determine the stages of the activities. In this regard highly complex tasks are listed at the top thereby the simple ones are listed at the bottom to make the project structure for proper marketing standards complying with the business needs of “ANR Robinson Airport”.
Communication plan
Description | Objective of communication | Frequency | Medium | Target Audience | Owner |
Verbal | Developing good relations and influencing stakeholders | High | Direct meeting, SMS, digital modes, calls | Employees, investors, legal stakeholders | Project manager and leaders |
Written | Sustain authenticity of the project steps and contracts | Medium | Letters, emails and text messages | Shareholders, government authorities and international organisations | Project leader |
Listening | Estimation and understanding of the project complexities, client requirements and customer retention | High | Telecommunicaction and research analysis | Employees and management | Marketing managers |
Virtual | Establishing quick and relied on communication | High | Online platforms, data base management systems | Clients, investors, partners and employees | Project manager |
Visual | Assigning proper marketing plan and checking its progress | Medium | Skilled asscaites, data tools and communication platforms | Stakeholders and customers | Managers and employees |
Table 1: Communication Plan
SN – Essential communication through different modes are required to be addressed with the help of “face-to-face”, “meeting”, “newsletters”, “reports” and others.
- The relevant stakeholders are customers and investors from the islands and the targeted external markets (Tse, 2022)
- Key planning considerations require entertaining in this regard namely “environmental considerations”, “mission assurance”, “force protection” and others.
- Proper relation-building for the market expansion of “ANR Robinson Airport” is a requirement
SN – Strategies are needed to be enlisted for better management of the operations and creating an effective business environment.
WBS
Figure 1: Work Breakdown Structure
SN – The WBS structure includes three stages and each of them is associated with the marketing plan for “ANS Robinson Airport” Marketing plan development. The plan accommodates facility building to digital inclusion in all stages systematically to increase customer inclusion in the management of the operations.
Activity list
Activity number | Description | Duration | Preceding Activity |
“Project objectives”
|
Designing facilities
Development of the tourism Increase the customer and stakeholder engagements Sustainable economy including environmental actions |
14 days (Started on 1st Nov 2022)
(1’st November-18’th November) |
None |
“Cost estimation” | Determine marketing costs
Facility building costs Renovation costs |
10 days
(21’stNovember-2’ndDecember) |
“Project objectives” |
“Time estimation” | Project planning
Time for technical inclusion Allocation of skills Project execution |
33 days
(5’th December-18’th January) |
“Cost estimation” |
“Constraints and assumptions” | Competition
Funding Skills Planning |
62 days
(19’th January-13’th April) |
“Time estimation” |
“Communication plan” | Customer communication
Stakeholder engagement Legal communication |
17 days
(14’th April-8’th May) |
“Constraints and assumptions” |
“Risk management” | Implementation of mix marketing
Contingency funds Loyalty programmes Employee benefits |
41 days
(9’th May-4’th July) |
“Communication plan” |
“Activity plan” | Resource allocation
Structural design Digital inclusion |
37 days
(5’th July-24’th Aug) |
“Risk management” |
Table 2: Activity List
SN – The activity lists include structural designs the marketing plan to be executed by “ANR Robinson Airport” to comply with the business requirements and marketing plan development.
The network diagram and critical path
ANR ROBINSON INTERNATIONAL AIRPORT MARKETING PROJECT | DURATION IN DAYS | Predecessors | |
A | Project overview | 119 | |
B | Cost estimation | 10 | A |
C | Time estimation | 33 | A, B |
D | Constraints and assumptions | 62 | C |
E | Communication plan | 42 | D,C |
F | Activity plan | 13 | E |
Figure 2: Network Diagram
Critical Path can be:
A-B-C-D-E-F
OR
A-C-D-E-F
Total days to accomplish the project: 269 days
SN – Critical analysis on the ground of marketing plan development has to be included in a proper manner to synchronies all the stages for better inclusion of clients. In this regard essential stages are aligned and displayed in the research.
Risk register
Risk log | |||||||||
Project: Status/Version:
Author: Date: Distribution: |
|||||||||
Ref. | Date raised | Risk description | Probability (P) | Impact (I)
|
Risk rating (P*I) | Managed responses | |||
Action | responsibility | Review date | Status | ||||||
1. | 3rd Nov 2022 | Difficulty in time management | 4 | 5 | 20 | Monitoring | Project manager | 10th Nov 2022 | Resolved |
2. | 5th November 2022 | technological risk | 5 | 5 | 25 | Inclusion of technology | Project engineer | 15th November | Going on |
3. | 10th November 2022 | health, and safety risk | 3 | 4 | 12 | Safety regulations | Operational manager | 16th November 2022 | Resolved |
4. | 15th November 2022 | economical risk | 4 | 4 | 16 | Revision of budget | Finance department | NA | Unresolved |
5. | 20th November 2022 | social risk | 4 | 3 | 12 | Planning for communication | Project manager | 25th November 2022 | Resolved |
6. | 25th November | communication risk | 5 | 4 | 20 | Restructuring relations | Project manager | 5th December 2022 | Going on |
Table 3: Risk Register
References
Huo, B. and Guo, M., 2021. How does an aerotropolis integrate? A case from Zhengzhou airport economy zone. Logistics, 5(2), p.26.
Pocinho, M., Vieira, N.G.S., Nunes, C. and Nechita, F., 2021. Sustainable customer digital engagement strategies for the tourism recovery perspective. Bulletin of the Transilvania University of Brasov. Series V: Economic Sciences, pp.51-62.
Kopasz, J. and Krause, T., 2021. H2@ Airports Workshop Summary Report (No. ANL-21/61). Argonne National Lab.(ANL), Argonne, IL (United States).
Karayev, S., Zhangazina, U., Nurtillayev, B., Saipyrkhan, D. and Zaitov, M., 2021. Marketing in Event Management, Astana EXPO2017.
Layton, R.A. and Domegan, C., 2021. The next normal for marketing—The dynamics of a pandemic, provisioning systems, and the changing patterns of daily life. Australasian Marketing Journal, 29(1), pp.4-14.
Fischer, B., 2022. A modality innovation approach: How can royal schiphol group identify and select future proof forms of mobility?.
Know more about UniqueSubmission’s other writing services:
Malatya Karaca Ticaret | NURKAN KARACA Malatya stihl bayi,Malatya stihl servis,Hızar motoru,Motorlu testere,Motorlu tırpan, Çim biçme makinası,Malatya karacalar,Malatya stihl, nurkan karaca Malatya’nın en köklü Stihl bayilerinden olan Nazım Karaca ve torunu Nurkan Karaca şimdi e-ticaret platformlarında faaliyet yürütmektedir. Mağazamız, hem stihl satışı hem de stihl servisliğini yapmaktadır.
Malatya Karaca Ticaret | NURKAN KARACA Malatya stihl bayi,Malatya stihl servis,Hızar motoru,Motorlu testere,Motorlu tırpan, Çim biçme makinası,Malatya karacalar,Malatya stihl, nurkan karaca Malatya’nın en köklü Stihl bayilerinden olan Nazım Karaca ve torunu Nurkan Karaca şimdi e-ticaret platformlarında faaliyet yürütmektedir. Mağazamız, hem stihl satışı hem de stihl servisliğini yapmaktadır.