BSS060 Project Management Assignment Sample 

Introduction

A project contains various elements that needs to be specified in effective way. There is a DDM company that has decided to do a virtual management conference. This is because of ease on covid 19 measures (Dawson and Dawson, 2021). So, a project has been undertaken by whose objectives are as follows

Project objectives

  • To conduct a hybrid Digital management conference in Birmingham, England.
  • To do conference to differentiate themselves from other.
  • To cover on topics of data analytics, AI, cyber security and others.

Expected benefits

  • The main benefit is project will help DDM to differentiate them in market.
  • Also, through it they can attract more customers and also gain more subscription of magazine.

Estimated cost

Every project includes a cost on basis of which it has to be completed. Then, budget is prepared and allocation of resources is done. Hence, the budget of current project is £350,000. It is given as :

Activities Cost
Rent of venue  £115,000
Speakers cost  £17,000
Security services  £29,000
Catering services  £25,000
HR  £16000
Other expenses  £10,000

Timescale

Get Assignment Help from Industry Expert Writers (1)

It is important to complete project on time. This is because if there is any delay in it then cost rises and also project goals are affected. In digital conference project it will begin in April 2022 and end in October 2022. So, total 7 months are there.

Assumptions

In project there can occur some assumptions which are unexpected. They can impact on project negatively (de Falco and Macchiaroli, 2020). However, the manager is responsible for managing assumptions by taking relevant measures. Thus, in present project assumptions are as below:

  • The catering facilities are not finished in time at venue
  • There are limited health and safety measures taken.
  • There can occur technical issue in IT software and speakers.
  • HR is not trained well enough to perform activities in project.
  • There may be lack of funds or labour on venue.
  • There are travel problems for guests to reach on venue.
  • No proper arrangement of 500 guests at venue.
  • Resources can be insufficient due to which project is not finished on time.

Constraints

Also, there are several barriers which may occur as well. It may be due to ineffective planning or any other critical situation. So, constraints are defined as:

  • There can be delay in project because of any situation.
  • The cost can rise because of delay in project (Mainul Islam and Faniran, 2019).
  • At time of conference IT failure may occur or security issue can arise.
  • There are improper arrangements of catering services at venue.

Communication plan

Get Assignment Help from Industry Expert Writers (1)

It is important to develop a communication plan. It is because it shows that what type of info is to be shared with whom stakeholders. Besides that, it will also show when and how many times info is to be shared. Hence, project manager is easily able to share info in effective and systematic way with stakeholders. Thus, the plan is mentioned as below:

Description Objective of communication Frequency Medium Target audience Owner
Communication type What is trying to achieve How often it happens Method Who will receive communication Who is responsible
Event planning Once in week Through  meeting Project team, DDM director and stakeholders Project manager
Roles and responsibility Daily Through e mail Project team Project manager
Project progress Once in week By e mail Project team, DDM management and stakeholders DDM director
Ticket sells Once in month By e mail Stakeholders Project team

WBS

The WBS is break down of entire project into hierarchal way. It gives overview of tasks to be done. This makes easy to proceed into project in step in step way (Rettig and Simons, 2018). In same way, for conference project WBS is

Partial activity of conference

Task Name Duration Start Finish Predecessors
Planning 55 days Mon 11-04-22 Fri 24-06-22
   Preparing budget 4 wks Mon 11-04-22 Fri 06-05-22
   Selection of venue 2 wks Mon 09-05-22 Fri 20-05-22 2
   Booking venue 2 wks Mon 23-05-22 Fri 03-06-22 3
   Catering arrangement 3 wks Mon 06-06-22 Fri 24-06-22 4
Guest 10 days Mon 27-06-22 Fri 08-07-22 4
   Guest list 2 wks Mon 27-06-22 Fri 08-07-22 5
Speakers 10 days Mon 11-07-22 Fri 22-07-22 5
   Arranging speakers 2 wks Mon 11-07-22 Fri 22-07-22 7
Event promotion 35 days Mon 25-07-22 Fri 09-09-22 7
   Printing flyers 3 wks Mon 25-07-22 Fri 12-08-22 9
   Ticket selling 4 wks Mon 15-08-22 Fri 09-09-22 11
Registration 2 wks Mon 12-09-22 Fri 23-09-22 12

Converting activity list into AoN diagram

 

BSS060 Project Management
BSS060 Project Management

 

BSS060 Project Management
BSS060 Project Management

Activity box

Early start Early finish
Float Activity description Duration
Late start Late finish

Forward pass

Activity Duration Preceding Activity
A 4
B 2 A

Activity

Activity Description Duration Predecessors
A    Preparing budget 4 wks
B    Selection of venue 2 wks A
C    Booking venue 2 wks B
D    Catering arrangement 3 wks C
E    Guest list 2 wks D
F    Arranging speakers 2 wks E
G    Printing flyers 3 wks F
H    Ticket selling 4 wks G
I Registration 2 wks H

Dummy start activity

Activity Description Duration Predecessors
A    Preparing budget 4 wks
B    Selection of venue 2 wks
C    Booking venue 2 wks A
D    Catering arrangement 3 wks B
E    Guest list 2 wks C, D
F    Arranging speakers 2 wks E
G    Printing flyers 3 wks F
H    Ticket selling 4 wks G
I Registration 2 wks H

Backward pass

Early start Early finish
Float Activity description Duration
Late start Late finish

Risk register

There are different types of risk that can occur into project. It is important to find out those risks so that measures are taken to mitigate it otherwise project can be affected negatively. However, on basis of project size and type, risks occur (Thomas and Kihneman-Wooten, 2017). In similar way, in digital conference project risk register made is

 

Date

 

Risk description

 

Probability

 

Impact

 

Risk rating

Managed response
Action Responsibility Review date Status
1 Delay in completion of project 5 6 30 There must be schedule prepared and then progress is measured. Project manager 5-5-2022 Done
2 The budget may increase 3 5 15 There should be back up of additional funds maintained. Finance team 7-6-2022 In progress
3 Risk related to health and safety issues 2 6 12 There can be inspection done to check safety measures Project manager 8-7-2022 Done
4 Technical error or issue in IT software 2 5 10 All equipment can be tested and checked. Moreover, before event testing as well as inspection can be done. IT team 23-7-2022 Delay
5 Risk of lack of resources 3 2 6 It should be ensured that resources are utilized in effective way. Project manager 10-9-2022 Done

References

Dawson, R.J. and Dawson, C.W., (2021). Practical proposals for managing uncertainty and risk in project planning. International Journal of Project Management1i6(5), pp.299-310.

de Falco, M. and Macchiaroli, R., (2020). Timing of control activities in project planning. International Journal of Project Management, 16(1), pp.51-58.

Mainul Islam, M.D. and Faniran, O.O., (2019). Structural equation model of project planning effectiveness. Construction Management and Economics, 23(2), pp.215-223.

Rettig, M. and Simons, G., (2018). A project planning and development Burman, P.J., 1972. Precedence networks for project planning and control.process for small teams. Communications of the ACM, 36(10), pp.45-55.

Thomas, M. and Kihneman-Wooten, J., (2017). Developing an effective project: Planning and team building combined. Project Management Journal, 39(4), pp.105-113.

Know more about UniqueSubmission’s other writing services:

Assignment Writing Help

Essay Writing Help

Dissertation Writing Help

Case Studies Writing Help

MYOB Perdisco Assignment Help

Presentation Assignment Help

Proofreading & Editing Help

Leave a Comment