Assignment Sample on CONM40012 Project Initiation

Task 2: Project Initiation Document

Introduction

For the proper conduction of this project work there needs to be effective implementation of the initiation works. There needs to be an appropriate management process for the success of the project work including the initiation process for that project work. There are different types of factors that could affect the overall initiation process of the project. For that, these factors also need to be managed properly with the help of the project management process. The documentation for the project initiation works is essential and useful for the overall understanding of the range of the project and also for the required declaration for different works for that project. The initiation of the project is important for the further works or stages of the project works. The reason, abilities, and execution of the project work depend on the proper documentation of the project initiation works. These types of documents are essential for the proper justification of the project works.

Project Overview

This is a “Grade A” office construction that intends to provide around 4645.152 square meters of spacing for that well-connected location of Nottingham. The site which is proposed is in the 11 station street. This is situated in the center of the city and directly opposite the train station of Nottingham (Mandala, 2018). The train interchange is also easily available for this location advantage. There could be also cultural exchange due to the centre location of the city. For the improvement of the refurbished commercial and new build in Nottingham, there need to be appropriate project management processes. The client of this project is Bildurn which is an award-winning and privately owned manager and developer for the commercial based buildings of the Nottingham area. For the improvement of the sustainability of the project, these types of management activities really essential. There are location advantages for these types of projects and for that there is enough demand for this type of commercial buildings and as well as the developing projects related to that. There are also certain goals and objectives for this type of project. These objectives are chosen depending on the market demand and the changing trend of these markets. The business plan of the clients also needs to be considered as the main factor for this type of project activity. The main objective of this project is to provide sustainability for the working structure for different types of project works. This will help to improve the quality and process of the project work. Appropriate project management activities are essential for the betterment of the project work and also for the success of that project. If there is the proper use of these types of project management and management tools there could be the determination of the challenging factors and risks for that project and project world.

Time estimate for the Project

The proper estimation of the time and other factors are important for the successful conduction of the project. For the creation of appropriate planning or structure for this type of construction and management work there need to be accurate time estimation for the project. There need to be proper implementation of the “high-level” time estimation plans and structures for this project. There could be different types of project activities that need to be used for the time estimation for this project. For the initial stages of these types of projects, there is a need to be an appropriate appraisal of that project (Dovleac and Ionică, 2017). After the initial stages of this project, there need to the proper designing for the success of that project and project works. The cost of that project also needs to be considered for the proper conduction of the project works. For that, there needs to be an effective collection process of the related data and datasets for this type of the research project. After that, there are the tendering related works for this research project. Lastly, there would be the construction works as desired for those projects. After the completion of this project work, there will be a proper handover process for the declaration of the success of this project. The required time ad duration of this project could also be determined for the creation of the proper strategies for the management and project activities for the success of this project. Different types of challenges and obstacles are also could be determined for this type of project. The former similar project works and related estimations are also could be used for the creation of the time estimation plan or proper timing for different types of activities for these projects. The reliabilities and uncertainties for these types of projects are also could be determined with the help of these types of project works.

Risk management

Get Assignment Help from Industry Expert Writers (1)

There could be different types of risks related to these types of construction and improvement projects. These risks are related to different factors of the industry. There could be technology risks for this type of research project. These risk factors need to be properly managed for preventing the creation of any type of challenging situation for that project. There are also risks for the communication related to the project activities. There could also be the creep risks related to the scope of the activities for this project. The costing of this type of project are also dependent on different types of situations relate to the market of that business and for that, there is also the probable risk factor for the cost of this project. The operations which are require for this project need to be managed as the operational risks for this type of project. There could also be a lack of the required skills for the successful completion of this project and for there could be probable risks for the successful completion of this type of research project. For the proper agent of these risks and risk factors, there need to be appropriate implications of the appropriate risk management processes (Janné and Fredriksson, 2019). There are different steps for the proper management of this type of project works. At first, the probable project risks need to be identified for the creation of the appropriate strategies according to the situation of that risk. After that, there needs to be an appropriate and effective process of analysis of those risks and risk factors related to that project. The process of prioritization of those risks and risk factors are also important for the creation of the appropriate management for those risks of that project. The potentials for these risks are also need to be analyzed properly for the improvement of the risk management technique and tools for that. After that, assigning works for those risks and risk factors are essential for the proper management of those works. Lastly, the proper monitoring and responding process or the proper management of that project are also important for the project. This will bring the required and effective risk management for that project.

Matrix for Responsibility Assignment

The “responsibility Assessment Matrix” (RAM) are essential for the proper assessment of the participation of different organizations. The individuals of the company and their role of them in this type of project are could be effectively assessed by that. This type of assessment method is used by the proper manager (PM) for the clarification of the responsibilities and roles of the multi-function teams for this project. The matrix of the RAM is also known as the “responsible Accountable Consulted informed” (RACI) matrix (Fesenko et al. 2018). This type of matrix could be developed by different stages. Ineffective project management works this type of matrix for assessment or RAM is used as an effective communication tool for the proper management of that project work. Different types of activities are also connected with this risk management works for that project. The RAM process and create an appropriate and effective chart of structure for the proper communication for the success of the project. The proper and effective communication between the team members of the project is the key factor for the successful project management works.

Conclusion

These types of initiation documents are essential for the successful conduction and proper management work of that project. There are different types of key factors for the betterment of the project and these are could be critically used for the proper conduction of this project. There also could be different types of risk factors for the conduction of these types of projects. These risk and risk factors are also could be effectively handled by the effective use and creation of the risk management structure for that project. There could also be different effective methods for the assessment and creation of the required connection among the project work. There are different types of matrices for the betterment of risk management works. Among them, the “Risk assessment Matrix” (RAM) is one of the most effective and used matrices for this type of activity for the improvement of the project management works.

 

 

Task 3: Development Appraisal and Cost Estimate

Introduction

For any type of construction project, the pre-estimation of the cost and also the assessment of the probable risks for that project need to be discovered for the betterment and also for clear evaluation of that project. For the creation of the appropriate cost estimation of that project there needs to be a proper collection of the related data and information for that project. Different factors related to that project need to be clarified for an accurate estimation of the cost of that project. The success of that project depends on the proper cost estimation for that project. Depending on the cost estimated factors there is the creation of the appropriate and proper planning for that project. There is also an effective process for the development appraisal for that project. The process for the development appraisal involves certain stages for the success of such activities. For the proper planning depending on the physical characteristics, the company needs to use a proper development appraisal process.

Cost Estimation

Get Assignment Help from Industry Expert Writers (1)

The Cost estimation process for that project needs to be relatable and accurate for the clear observation for that project. There are certain ASSUMPTIONS FOR THE CREATION OF THAT COST ESTIMATION for that project. These assumptions could be really essential for the betterment of this type of project work. The “Estimate Base date” for the cost estimation is November 2021 and the pre-contract for that program will be around eight months.

Figure 1: Ground floor

(Source: provided)  

For the post-contract programs, the required time is going to be around twenty months. The professional fees for that project are going to be based on the price book of SPONS. For the preliminaries of the contractor, there is a 12% cost specified for that. The cost for the land including the land tax for that area is going to be  £600,000.IDC stands for interest during construction. It can be applied in a construction project in additional financing, project loans, development program loan, sector loan, and financial intermediation loans.

Figure 2: Different costing factors

(Source: Self created by using excel)

Interest expenses considerably play a vital role in increasing the construction cost (Peng et al. 2020). It could be calculated till the point at that point the construction to be completed and started producing benefits from the project. Planning permission is significant for a construction project such as structural changes in existing buildings, building new buildings, and changing the actuality of a business. The main aim of planning permission is council planning policies and maintenance with building rules and regulations. The planning permission requires submission of all kinds of documentation such as building plans with supporting documentation and paying the fee of planning permission.

Earthwork in an excavation in the foundation

This assignment mentions a building estimation sheet, in this sheet number of footing is 11, length of the footing is 2.2, the width of the footing is 2.2, and the height of the footing is 1.580, the quantity of footing is 84.12. Unit is cu m. The second heading is footing PCC, here take footing thickness is o.75, the number of footing PCC is 11 and breath 1.3, and the total quantity of footing PCC is 1.39. The height depth for the project will be 1.780.

Figure 3: Earthwork in excavation in the foundation

(Source: Self created by using excel)

Backfilling

Backfilling is one of the headings that need to be calculated in building an estimation quantity sheet. In backfilling heading there including a few eliminate to understand proper backfilling elements such as excavation area, deduction. All backfilling is considered in this sheet. The total backfilling quantity in this estimation is 77.16 cu m.

Figure 4: Back-falling estimation

(Source: self created by using excel)

Brick masonry

Brick masonry is the heading of the quantity sheet. Under the brick masonry, there are some sub-elements such as long wall, deduction, and 115mm thick wall brick masonry. The total quantity of thick walls is 24.49 cu m. The quantity of plaster is dependent on how thick the walls are going to be as the requirement of that project.

Figure 5: Brick Masonry from quantity sheet

(Source: Self created by using excel)

Inside plaster

Inside plaster one of the headings that are mentioned is the quantity sheet. In this heading, there are a few subheadings like bedroom and its deduction, kitchen plus dining and deduction, verandah and its deduction, DRG. room and its deduction, bathroom and its deduction, W.C and its deduction.

Figure 6: Inside plaster from quantity sheet

(Source: Self created by using excel)

 

Outside plaster

In the outside plaster heading, there are also some subheadings such as the front side and its deduction, backside and its deduction, right side and its deduction, left side and deduction and paper wall.

Figure 7: Outside plaster from quantity sheet

(Source: Self created by using excel)

Ceiling plaster

The ceiling plaster heading has some elements such as bed room, kitchen plus dining, verandah, DRG room, bathroom, W.C and passage. In the quantity sheet total outside quantity is 65.72 sq.m.

Figure 8:  Ceiling plaster from quantity sheet

(Source: Self created by using excel)

Slab RCC

In the cost estimation sheet or quantity sheet there are various slab mansions such as slab 1, slab2, slab 3 etc. In the quantity sheet total quantity of RCC slab is 12.59 cu m.

Figure 9: Slab RCC

(Source: Self created by using excel)

 

Column up to plinth level RCC

In the quantity sheet Column up to plinth level RCC total quantity is 4.95 cu m

Figure 10: Column up to plinth Level RCC

(Source: Self created by using excel)

 

For preparing a quantity sheet it should follow some step through methodology. Calculating quantity sheet need to follow step by step procedure. In this assignment mansion a quantity sheet based building estimation. There are a few group as heading and under the main heading there are some sub heading so that it understand clearly to project manager.

Figure 11: First floor

(Source: provided)  

Building estimation quantity helps to complete a project within time. A project manager takes decisions in order to complete a project; it helps to generate various kinds of decisions such as construction project estimation budget, various resources consumption, labor cost and many other things.

Figure: Building elevation

(Source: provided)  

In a construction based project it is very crucial to estimate the raw materials consumption because of raw materials such as cement, TMT bar etc. procure excess that is not used in this project so construction cost would be high and on the other hand if construction related materials procure inadequate its direct impact on project and it’s also increase the time duration and project cost that is not favorable for the project. Depend on the floor planning and elevations of that office building the cost estimation process have been performed. Building estimation quantity sheet also helps to prepare a new construction building project because project manager to initiative a new construction building project, in this case project manager first duty to see previous quantity sheet so that its helps to preparing budget estimation of current project.

Figure 12: Quantity of costing

(Source:https://accountinguide.com/wp-content/uploads/2020/01/Quality-Control-e1588138676895.png)

 

 

Development appraisal

The development appraisal is an objective financial viability test for the ability of the development project to meet the cost planning forecast and it also ensures market risk-return in order for the project to be delivered. A financial liability is an objective in order from a valuation point of view. The project manager uses the residual method for valuing that recognizes the function in different elements (Wibowo and Uda, 2018). A well knowledgeable person will search market evidence for valuation. A value can evaluate the return of investment through the project analysis. In respect of planning, it involves various research and analysis into limitations and brings opportunities to evolve from the project location and planning the project feature of project place site as well its real characteristics. It can be a very complicated process in order to provide a document of basic guidance with respect to economic viability for planning. The document might set out when the proposed project or development will be affected by planning history, environment limitation, local plan, and local business. Two things happen when the planning obligation declines the place value for the landowner and the return on investment level is below the real level therefore development going to be distracted by development appraisal will not take the right place.

Figure 13: Risk allowance estimates

(Source: Self created by using excel)

There are a few factors that depend on whether a development appraisal is useful or not. Factors are Reviewing or analyzing the land uses, to evaluate the nature and the level of strategy obligation contribution. To complete the measure of affordable housing Risk allowances estimates such as design development, construction list, and employer’s other risk, Employer change risk. A large building project or residential house requires many decisions; it could be small or big. Building estimation follows some methods. For the further improvements on this project the related risk factors should also be evaluated and analyzed properly. To prepare building estimates there are some columns Serial number, item description, length, width, height, quantity, and unit. The serial number describes earthwork in an excavation in foundation here mansion footing, for creating cost estimation sheets needed for the footing.

Conclusion

This assignment is providing support to the project cost estimation and it also helps to revise the project cost. This assignment’s main aim is to understand the actual cost estimation process and also it is intended that a cost estimation is a significant tool for robust a project. Judgment depended on project cost forecasting and particular coaching should be sought where it is essential for example point out determining accurate price and physical contingencies or project cost list.

 

 

 

 

Task 4: Report on Project Carbon Reduction

Introduction

For these types of construction projects and project management their need to be the fulfillment of the requirements of the clients. In this project, there are requirements of a proper management structure for the reduction of the carbon emissions. This is a demand from a major founder of this project. Due to the climate change and other complications related with the environment there need to be a proper use of the project management works for that project. There could be different types of tools that could be effectively used for5 the betterment of the structure of development for the project management works. There could also be proper uses of the project management tools for the proper conduction of the project. If there is the success of the project management world for the reduction of the carbon emission due to this project, the demand for this type of project will rise along with the successful completion of that project. The proper initiatives are also essential for the betterment of the project management work and also for the improvement of the desired objectives of that project. With the proper management is the desired objectives of the project the sustainability of the project are also need to be maintained for this type of assessment and implications for the project.

Aim and Objectives

Aim of the project

The main aim of this type of project work is to consider the factors related the climate change and to implicate proper tools for the reduction of carbon emission from these types of project works. The assessment for the project management work for this project objective is also another aim for this project.

Objectives

  • To analyze the role of the project management in tackling the climate change
  • To identify the initiatives this could be implicated for this type of project for the reduction of the carbon emission from these construction work for the project.

Role of the Project Manager

For the control of the overpressure of these types of construction projects, there need to be appropriate management works which are essential for the success for that project success. For this type of activities for the project management projects, there would be fulfillment of the project objectives which are required for the betterment of this types of projects. Proper measurement, control and management of this type of project activity are essential for the betterment of the project and also for achieving the project activities for the project. The whole initiatives are needed to be managed and controlled with proper monitoring of the project work for the fulfillment of the objectives like the reduction of the carbon emission from the construction sites. There also could be different challenging factors that could affect the working structure of this type of project works. For that, these factors also need to be properly analyzed and measured for the betterment of the project assessment and conduction structure for that certain project. The project manager ensures that the whole project completes in a time period. As project manager of a project, look at all kinds of factors of a project to meet the project expectation that could be outside and inside during the whole life cycle of a project. The project manager, direct the consumption of resources and also responsible for the life cycle mentality of the project. A project manager’s significant responsibility is the inception of all the factors that are included in the project and also surveillance that properly dispose of project resources. The project manager makes decisions based on the environment, public interest, and social interest. Another project manager’s important role is that the project manager balances sustainability of a project. The project manager always follows some principle that must be strategic. The project manager will take action in a responsible way that must be good environmentally and socially.

Reduction of carbon emission

Globally poverty reduction through economic development is the main aim therefore rapid development is a significant key to meeting the global demand however development could result in increased environmental pollution such as greenhouse gas. In a construction project, there are lots of issues in the environment so it needs to be important to identify the carbon emission area of a project and also try to minimize the risk. It is one of the problematic edges of a project; as a result, the project could be delayed if the proper solution is not found as soon as possible. Greenhouse gas vastly impacts the environment as a result it creates various problematic issues. Currently, there are various tools and data to support carbon die oxide impact analysis in the construction section used for creating a framework in order to measure the carbon footprint that measures the mechanism of building construction. Construction building emissions are normally small but they can be important in a few cases (Willhelm Abeydeera et al. 2019). Carbon emission from expressways is more than railways, it works as in building construction there need various resources therefore it’s important that a project manager must ensure all resources come into the project site through railways, it helps reduce carbon emission.

Implications of appropriate initiatives

In a project, a project manager developed a carbon emission footprint and applied it in this study to be further increased in building construction projects. It can support periodic assessment of development in reducing carbon die oxide. It also helps to better surveillance of the carbon dye oxide. Reducing and monitoring carbon emissions will have various resource implications. It needs to be deliberated with the client over country programming. In communication with bilateral development and multilateral development, a project manager might consider developing the tools for the forecast of carbon emission of the building project and applying it to select as per pilot basis.

Conclusion

This assignment gives knowledge that the role of a project manager is significant as the project manager decides how a project will be driven. The accountability may change based on the type of project but the methodologies of a project such as a construction-based project would be the same. Project manager has some important key mansions previously and the project manager must follow invariably and always try to give their best at any kind of situation. A construction-based project would be successful when all the factors meet properly and all the team members coordinate well therefore it needs combined efforts on both sides. A project manager manages all the teams. It shows how a successful project accomplishes efficiently.

 

 

 

Reference List

Journals

Aarikka-Stenroos, L., Aaboen, L., Cova, B. and Rolfsen, A., 2018. Building B2B relationships via initiation contributors: Three cases from the Norwegian-South Korean international project business. Industrial Marketing Management68, pp.74-85.

Dong, L., Wang, Y., Li, H.X., Jiang, B. and Al-Hussein, M., 2018. Carbon reduction measures-based LCA of prefabricated temporary housing with renewable energy systems. Sustainability10(3), p.718.

Dovleac, R. and Ionică, A., 2017. Quality management techniques embedded in Agile project development. In MATEC web of conferences (Vol. 121, p. 05003). EDP Sciences.

Fesenko, T., Shakhov, A., Fesenko, G., Bibik, N. and Tupchenko, V., 2018. Modeling of customer oriented construction project management using the gender logic systems. Eastern-European Journal of Enterprise Technologies1(3), p.91.

Halttula, H., Haapasalo, H., Aapaoja, A. and Manninen, S., 2017. Early involvement and integration in construction projects: the benefits of DfX in elimination of wastes. International Journal of Management, Knowledge and Learning6(2), pp.215-237.

Janné, M. and Fredriksson, A., 2019. Construction logistics governing guidelines in urban development projects. Construction innovation.

Khan, R.A. and Gul, W., 2017, September. Emperical study of critical risk factors causing delays in construction projects. In 2017 9th IEEE International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS) (Vol. 2, pp. 900-906). IEEE.

Kim, M.H., Lee, E.B. and Choi, H.S., 2018. Detail engineering completion rating index system (DECRIS) for optimal initiation of construction works to improve contractors’ schedule-cost performance for offshore oil and gas EPC projects. Sustainability10(7), p.2469.

Li, Y. and Liu, C., 2019. Applications of multirotor drone technologies in construction management. International Journal of Construction Management19(5), pp.401-412.

Mandala, E., 2018. Influence of stakeholder’s involvement in project management on the performance of road construction projects in Kenya: a case of Bondo sub county, Siaya county (Doctoral dissertation, University of Nairobi).

Peng, H., Zhang, W., Song, Y., Yin, F., Zhang, C. and Zhang, L., 2020. In situ construction of Co/Co3O4 with N-doped porous carbon as a bifunctional electrocatalyst for oxygen reduction and oxygen evolution reactions. Catalysis Today355, pp.286-294.

Prasad, K.V., Vasugi, V., Venkatesan, R. and Bhat, N., 2019. Analysis of causes of delay in Indian construction projects and mitigation measures. Journal of Financial Management of Property and Construction.

Wibowo, M.A. and Uda, S.A.K., 2018. Reducing carbon emission in construction base on project life cycle (PLC). In MATEC Web of Conferences (Vol. 195, p. 06002). EDP Sciences.

Willhelm Abeydeera, L.H.U., Wadu Mesthrige, J. and Samarasinghalage, T.I., 2019. Perception of embodied carbon mitigation strategies: The case of Sri Lankan construction industry. Sustainability11(11), p.3030.

Wu, G., Yang, R., Li, L., Bi, X., Liu, B., Li, S. and Zhou, S., 2019. Factors influencing the application of prefabricated construction in China: From perspectives of technology promotion and cleaner production. Journal of Cleaner Production219, pp.753-762.

 

 

 

 

 

 

1 Comment

Leave a Comment